 |
By
Mohan Thiagarajah, Applications Consultant, Honeywell UK
Amoco
Valhall is an oil field which is located on the maritime border between
Norway and UK. It was put into production in 1982, and is currently
producing around 100,000 barrels per day.
Introduction
In 1998, Honeywell in Norway received a $1
million order to retrofit the turbomachinery control and condition
monitoring systems. The main objective of this retrofit is to maximize
oil production, which in turn requires gas production to be maximized.
This can only be achieved by running both parallel gas production
streams at full load. However, such operations are not possible with the
existing turbomachinery controls, mainly due to their dated and
inflexible designs.
The platform has two 'strings of compression',
each with four compressors stages driven by two Rolls-Royce Avon gas
turbines and a fifth driven by a gas expander. Both strings are
identical and arranged for cascade gas compression. The diagram below
shows a Rolls-Royce Avon driving a two-stage compressor.
| Honeywell also
supplied a VisSim model-based dynamic simulator to test the system
thoroughly during the factory acceptance test (FAT) and thus avoid
unnecessary delays during commissioning. This will be combined with
Amoco's spares to construct a realistic training aid. |

A Rolls-Royce Avon Driving A Two-Stage
Compressor. |
The Role of VisSim
VisSim was used to simulate 2 electric motors, 4
Rolls-Royce Avon gas turbines, 10 compressors, 10 re-cycle valves and 10
flow measurement elements. All these models were linked to Computer
Boards I/O cards via VisSim/Real-TimePRO. This allowed us to test the
all the controller / control modes simultaneously. Thus we were able to
start-up any or all of the turbo-compressors, run them in series /
parallel load-sharing configurations, and then shut them down at will.
The result was that control system became operational at the press of
the button. Amoco was able to start and get machines on-line in a manner
that was unheard of previously.
| The VisSim model
building exercise took two months of engineering. It was worth it
because the Amoco Project Manager (Karl Ole Stones) was convinced
that the modeling exercise saved 21 days of off-shore commissioning.
In terms of financial gain, this equates to:
(21 days) x (100,000 barrels per day) x
($15 per barrels) = $millions
Conclusion
So the moral of this story is 'a stitch in time saves nine'. |
|
"As a mechanical engineer, my main role at
Honeywell is to solve turbomahinery control problems - not learn
complex programming languages and simulation environments. So when I
was tasked with simulating turbomachinery to test control systems
before they left our factory, I chose VisSim. All you need is a
logical brain and some knowledge of engineering mathematics. VisSim
makes the rest very simple.
I was able to use its intuitive programming environment to create
very complex gas turbine and compressor models. They were so good
that the control systems that we tested became 'plug-n-play' items
in the field. This is previously unheard of. Many other control
system suppliers deliver 'plug-n-pray' items which are debugged
through 'trial and horror' at the customers expense."
Mohan Thiagarajah |
|
 |